TM 9-2320-269-20-2
CONSOLE COVER - CONTINUED
INSTALLATION - CONTINUED
NOTE
FOLLOW-ON MAINTENANCE: Connect battery ground cable (page 2-414).
TASK ENDS HERE
TELESCOPIC TUBES
This task covers:
INITIAL SETUP
Tools
Materials/Parts
Nuts, elastic stop (six required)
Pliers, slip-joint, angle-nose
Pins, cotter (three required)
Wrench, open-end, 9/16-inch
Personnel Required
Two
ACTION
LOCATION
ITEM
REMARKS
REMOVAL
1.
Three derrick
Three cotter pins
a. Using slip-joint pliers, straighten
operator's valve
(3) and pins (4)
pin (3) ends, and pull out.
spools (1) and
b. Get rid of cotter pins (3).
yokes (2)
c. Using slip-joint pliers, pull out
pins (4).
2.
Three derrick
Three yokes (2)
Move away from.
operator's valve
spools (1)
3.
Bracket (5) and
Three screws (7)
a. Using 9/16-inch socket, handle, and
tube bracket (6)
and elastic stop
9/16-inch wrench, unscrew and take
nuts (8)
out.
b. Get rid of nuts (8).
2-1094